SLCC Milestones

 

Based upon anticipated enrollment growth 2008-2028, SLCC has identified a need for approximately 570,000 gross square feet of new space to support 9,200 new FTE students; this space may be owned or leased, depending on location and circumstances. In addition, there will also be a need for ongoing renewal of existing facilities to increase utilization and respond to evolving program requirements, as well as replacement of existing obsolete or unserviceable buildings that have exceeded their useful life spans. Milestones for new construction projects are proposed in five-year increments. Development of new facilities in the Southwest and Northwest areas can be deferred until anticipated population growth has clearly established the need for expanded service in these locations.

  2008-2013 2013-2018 2018-2023 2023-2028
General Increase utilization & renovate as needed to support programs Increase utilization & renovate as needed to support programs Renovate as needed to support programs
New eCampus building
Renovate as needed to support programs
Taylorsville

New Instructional Administration building
130,000 GSF

New Business Building
80,000 GSF
Two new sites at existing Admin.Bldg site
100,000 GSFx2 = 200,000 GSF
 
Jordan        
South City Center for New Media & Performance Hall
net gain 35,500 GSF
     
Miller        
Meadowbrook New building
29,000
Replace/Renovate existing buildings Replace/Renovate existing buildings Replace/Renovate existing buildings
Highland Center        
Airport Center   Expand or relocate at airport    
Library Sq Center   Acquire additional space in current building    
Rose Park Center        
Northwest Location     Develop new site
120,000 GSF
 
Southeast Location Develop new site
120,000 GSF
     
Southwest Location Develop new site
90,000 GSF
     
Total Building Area 520,000 GSF 120,000 GSF 120,000 GSF 70,000 GSF
Projected Enrollment Growth 2,300 FTE’s 2,300 FTE’s 2,300 FTE’s 2,300 FTE’s